Guide outline

ILIllinois

Illinois Lien Deadlines for Material Suppliers

Illinois requires a Notice of Intent to Lien within 90 days of your last furnishing. For single-family owner-occupied projects, notice is due within 60 days of starting work.

Public date calculations cover Florida and Kansas. Illinois dates require qualified review.

Illinois is High Risk for Suppliers

Illinois has a 90-day Notice of Intent to Lien requirement from last furnishing. However, if you are working on a single-family owner-occupied project, you must provide notice within 60 days of starting work. Missing these notices puts your lien rights at risk.

Illinois Mechanics Lien Deadlines (Updated 2026)

Scroll sideways to see all deadline details.

Deadline TypeTimingDetails
Preliminary/NoticeNotice of Intent to Lien — within 90 days of last furnishingRequired.
Special NoticeWithin 60 days of starting workFor single-family owner-occupied projects.
Lien Filing4 months after completionMust file lien by 4 months after completion.
Enforcement2 years after completionSuit to enforce must be filed within 2 years after completion.
Statutes770 ILCS 60/7; 770 ILCS 60/21

Common Supplier Mistakes in Illinois

Missing the 90-Day Notice

Failing to send the Notice of Intent to Lien within 90 days of your last furnishing is a critical error.

Missing the 60-Day Residential Notice

On single-family owner-occupied projects, you must send notice within 60 days of starting work, not just 90 days from last furnishing.

Late Lien Filing

The lien must be filed 4 months after completion. Missing this deadline invalidates the lien.

Missing Enforcement Deadline

Enforcement must occur within 2 years after completion.

Not Sure Which Deadline Applies?

Use this Illinois guide and collect your project facts for qualified review.

Review Illinois project facts

The public calculator provides dates only for reviewed Florida and Kansas scenarios; it does not calculate a Illinois date.

Frequently Asked Questions

When must the lien be filed?

4 months after completion.

What is the enforcement period?

2 years after completion.

What statutes apply?

770 ILCS 60/7; 770 ILCS 60/21.

When is the Notice of Intent to Lien due?

Within 90 days of last furnishing.

Is there a special rule for residential projects?

Yes, for single-family owner-occupied projects, notice is due within 60 days of starting work.