Maryland Lien Deadlines for Material Suppliers

Material suppliers in Maryland have specific rights to file a mechanics lien if they aren't paid. However, Maryland law requires strict adherence to notice and filing deadlines. If you miss a deadline by even one day, your lien rights may be extinguished forever. This guide outlines the critical steps for suppliers to secure their payment rights.

Public date calculations cover Florida and Kansas. Maryland dates require qualified review.

Maryland is High Risk for Suppliers

Maryland has strict deadlines. Always calculate your specific deadline based on your last furnishing date.

Maryland Mechanics Lien Deadlines (Updated 2026)

Scroll sideways to see all deadline details.

Deadline TypeTimingDetails
Lien Filing Deadline180 days from last furnishingMust be filed with the county recorder/clerk.
Enforcement Deadline1 year from petition filingLawsuit to foreclose on the lien must be filed by this date.
Preliminary NoticeNotice of lien claim within 120 days of last furnishingRequired to preserve your right to file a lien later.
StatutesGoverning statutesMd. Code, Real Prop. §9-104; §9-105; §9-109

Common Supplier Mistakes in Maryland

Missing the 120-day Notice of Lien Claim

Many suppliers fail to send the required preliminary notice early in the project, invalidating their future lien rights.

Filing the lien after 180 days

Waiting too long to file. The deadline is strict and often does not extend for weekends or holidays.

Missing the 1-year enforcement deadline

Filing a lien is not enough; you must enforce it (file a lawsuit) before the enforcement period expires.

Not Sure Which Deadline Applies?

Use this Maryland guide and collect your project facts for qualified review.

Review Maryland project facts

The public calculator provides dates only for reviewed Florida and Kansas scenarios; it does not calculate a Maryland date.