New Hampshire Lien Law Deadlines for Suppliers and Subcontractors

New Hampshire suppliers and subcontractors must give the owner written notice before furnishing and secure the lien by attachment in a court action within 120 days. Nothing is recorded with the county first: the lien lasts 120 days and then expires unless it is attached.

Public date calculations cover Florida and Kansas. New Hampshire dates require qualified review.

New Hampshire is High Risk for Suppliers

New Hampshire's lien lasts only 120 days, and there is no county filing to fall back on. You secure it by suing and attaching the property within that window. The notice to the owner before you furnish also matters: send it late and your lien shrinks to what is then due, or later becomes due, to the contractor.

New Hampshire Mechanics Lien Deadlines (Updated 2026)

Scroll sideways to see all deadline details.

Deadline TypeTimingDetails
Lien Attachment Deadline120 days from last furnishingNew Hampshire liens are not recorded as a standalone filing. The lien arises automatically and lasts 120 days after the labor is performed or the materials are furnished, so do not let early unpaid deliveries age. Secure it by attachment in a court action within that time; the writ of attachment is filed at the registry of deeds (RSA 447:9, 447:10, 511-A:8).
Preliminary NoticeWritten notice to the owner before furnishingIf you do not contract with the owner, give the owner or the person in charge of the property written notice before you furnish. A late notice limits your lien to what is then due, or later becomes due, to the contractor (RSA 447:5, 447:6).
30-Day AccountAt least every 30 daysAfter giving notice, give the owner an itemized written account at least once every 30 days (RSA 447:8).
Construction Lender NoticeWithin 15 business daysNotify the construction lender within 15 business days after the lender's posting or after you start furnishing, whichever is later. Missing it does not by itself invalidate the lien (RSA 447:12-b).
Enforcement Deadline120 days after last furnishingLawsuit to foreclose on the lien must be filed by this date. In New Hampshire that means starting the court action and securing the attachment within the 120 days; attachment can be sought ex parte, and the owner can ask for a prompt hearing (RSA 447:10, 511-A:8).
StatutesGoverning statutesN.H. Rev. Stat. §447:2 et seq.; RSA 511-A:8 on attachment.

Common Supplier Mistakes in New Hampshire

Supplying before giving written notice

New Hampshire's notice goes to the owner before you furnish. If it is late, your lien is limited to what is then due, or later becomes due, to the contractor.

Looking for a county office to record in

There is no county lien filing in New Hampshire. The lien is secured by attachment in a court action, and the writ of attachment is then filed at the registry of deeds.

Letting 120 days pass without an attachment

The lien lasts only 120 days. If you have not secured it by attachment by then, it is gone.

Not Sure Which New Hampshire Deadline Applies?

Use this New Hampshire guide and collect your project facts for qualified review.

Review New Hampshire project facts

The public calculator provides dates only for reviewed Florida and Kansas scenarios; it does not calculate a New Hampshire date.

Frequently Asked Questions

What are the New Hampshire lien law deadlines?

Give the owner written notice before you furnish, send an itemized account at least every 30 days, and secure the lien by attachment in a court action within 120 days after the labor or materials are furnished.

Does New Hampshire require a preliminary notice?

Yes, if you do not contract with the owner. Give the owner or the person in charge of the property written notice before you furnish. A late notice does not end the lien, but it limits it to what is then due, or later becomes due, to the contractor (RSA 447:5, 447:6). See our preliminary notice deadline guide for building notice into intake.

Do I record a New Hampshire lien with the county?

No. The lien arises automatically and lasts 120 days. You secure it by attachment in a court action within that time, and the writ of attachment is filed at the registry of deeds. Attachment can be sought ex parte, and the owner can ask for a prompt hearing (RSA 447:10, 511-A:8).

Are these the 2024 New Hampshire lien law deadlines?

Yes. RSA 447:5, 447:6, and 447:8 were last amended in 2012, effective January 1, 2013, and RSA 447:9 in 1991, so the notice and 120-day rules applied in 2024 and remain current as of our September 2026 review.