North Dakota Lien Deadlines for Material Suppliers

Pre-recording notice and pre-enforcement notice are different requirements; late filing also changes the available protection.

Try 3 free calculations, then create a free account No credit card required

North Dakota is High Risk for Suppliers

Chapter 35-27 separates supplier relationships, recording, owner notice and enforcement. Do not treat the ten-day notice as an early-project preliminary notice or assume every filing after ninety days is automatically void.

North Dakota Mechanics Lien Deadlines (Updated 2026)

Scroll sideways to see all deadline details.

Deadline TypeTimingDetails
Notice Before RecordingAt least ten days before recording, when §35-27-02(4) appliesFor the described indirect-contract relationship, send the notice of intent to the owner by certified mail. Identify the actual buyer and statutory scope before applying it.
Lien RecordingOrdinarily within 90 days after last furnishingFile with the county recorder under §§35-27-13 and -14. Section -14 permits later filing with losses involving bona fide purchasers, encumbrancers and owner payments; an outer limit of three years from first furnishing applies. Late recording is not equivalent to ordinary timely protection.
Notice Before EnforcementPersonal service at least ten days, or registered mail at least twenty days, before actionSection 35-27-24 separately requires notice to the owner before commencing enforcement. This is distinct from the pre-recording notice.
Enforcement and Lis PendensBoth within three years after recordingSection 35-27-25 requires an action and filed lis pendens. A compliant delivered and filed demand can shorten the period to thirty days.

Common Supplier Mistakes in North Dakota

Assuming the ten-day recording notice also covers enforcement

Calendar the two notices separately and preserve their different service evidence. A certified-mail record for one step does not establish compliance with the other.

Treating late recording as ordinary protection

Review intervening title interests and owner payments before relying on §35-27-14. A supplier with a late claim needs individual review, not an automatic assurance or automatic rejection.

Filing an action without lis pendens

The three-year limit requires both steps, and a qualifying demand can accelerate it. Give counsel the recorded lien, title information and any demand promptly.

Not Sure Which Deadline Applies?

Check which supplier deadlines the calculator can evaluate for your North Dakota project.

Check North Dakota project coverage

Coverage depends on the project type, who hired you, and the facts you can confirm.

Frequently Asked Questions

Does a late lien automatically lose every right?

Section 35-27-14 permits late filing subject to important losses and an outer period. The answer depends on payments, intervening interests and furnishing dates; the ninety-day ordinary window remains important.

Does the calculator provide the enforcement deadline?

No enforcement output is promised here. Preserve recording and notice evidence and have counsel review the action and lis-pendens requirements.

Does recording the claim complete enforcement?

No. Preserve the recording receipt and obtain qualified review of the separate enforcement action and applicable service requirements. A filing receipt does not show that every later step is complete.